Risk Level

The Level of Risk is the product of the risk likelihood and its potential severity.

It will be computed as follows:

Probability x Severity

Risk Level

Green.png

1, 2, or 3

Minimum

Light_Green.png

4 or 6

Low

Yellow.png

5, 8, or 9

Moderate

Orange.png

10, 12, or 16

High

Red.png

15, 20, or 25

Extreme

Example: If a Risk’s Probability is “Possible” and its Severity is “Minor”, the Risk Level will be computed as follows: 3 (Probability) x 2 (Severity) = 6. The Risk Level will, therefore, be considered as “Low” (image1.png) and appear as such in the matrix.