How to assign Cost Items in a non-uniform manner

No matter which Distribution type is the default, the one selected is considered a uniform assignment, meaning that the assignment is linear over the duration of the task.

In some situations, Project managers sometimes have the need to assign cost items in a non-uniform manner.

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select a project in the Project Data Selector.

  4. Select a task in the Gantt spreadsheet to display the Task panel.

  5. Select the Transactions & Cost Items tab (Cost).

  6. In the Cost Item Assignment card, click on the Uniform (Uniform) button to make it non-uniform (Non Uniform).

  7. Click on the More (MoreVertical) button, and select the Edit command to open the Cost Item Assignment dialog box.

  8. Enter the Total Units in each cell of the spreadsheet.

  9. Close the dialog box.