How to send Timesheets back for Rework

Sometimes Actual Effort values submitted for a task are not accepted by the Project Manager and are returned for rework to the Team Member. Rework is only available if the Status of the Timesheet is Submitted, Reviewed, or Approved.

  1. Log in to the HTML5 client.

  2. Select the Tracking tab available in the Work workspace.

  3. Select a project in the Project Data Selector.

  4. By default, the Timesheets Overview displays the Resource Timesheets for the Current Week. Select another time frame if needed.

Bulk action

The Timesheets Overview provides the list of Resource Timesheets, grouped by overall Status enabling bulk actions

  1. Click on the Rework button to send the timesheets back to the Team Members.

  2. The Status of the Timesheet changed to Rework.

  3. The Timesheets are moved to the Rework Status section.

One timesheet at a time

  1. In the Timesheets Overview, click on the Resource's name to switch to the Timesheet Details full screen view.

  2. Click on the Rework button to send the timesheet back to the Team Member.

  3. The Status of the Timesheet changed to Rework.

    Note

    Note that Non-Project tasks already approved by the Resource Manager cannot be sent to Rework.

    Tip

    The Project Manager can also Approve or Approve & Apply a specific Task Timesheets by clicking on the corresponding More (MoreVertical) button.

  4. The Timesheet is moved to the Rework Status section.