Conéctese al cliente HTML5.
Elija el espacio de trabajo Centro de proyectos y abra la Tarjeta de proyecto.
Elija la Pestaña Gantt.
Elija una tarea en la tabla de Gantt para ver el Panel de tarea.
[en] Resources can only be assigned uniformly, and the Distribution type defined in the Project Card, Administration tab, Setup sub-tab, Resource Management section will be honored.
[en] In the Resource Panel, hover the left-hand side of the Resource row to display the "hand" icon.
[en] Right-click on the mouse and drag the resource on the Task row in the Tabla de Gantt.
[en] Drop the resource.
[en] In the Resource Panel, tick the check boxes available on the left-hand side of the Resources rows.
[en] Hover the left-hand side of one of the resources you ticked to display the "hand" icon.
[en] Right-click on the mouse and drag the resources on the Task row in the Gantt spreadsheet.
[en] Drop the resources.