Team Member

Take a tour of all workspaces and views related to this topic.

Timesheet workspace

The main purpose of this workspace is to allow Team Members to report the amount of time they have actually worked on the tasks they were assigned to (or on tasks that they were not originally assigned to).

Warning

Depending on the options selected by the Administrator in the System Settings workspace, features or displayed information can differ from one system to another.

Timesheet_workspace.png

The Timesheet workspace is made up of different sections:

Timesheet cards panel

The Timesheet cards panel displays the Timesheet cards ( i.e. one Timesheet card per week.) for the selected month.

Timesheet_cards_panel.png

Each Timesheet card comes with one of the following statuses:

  • This week – Actuals have been or need to be entered, moving the Timesheet from a non-working (inactive) phase to a working (active) phase.

  • Submitted – A Submit command has been executed, submitting the Actuals to the Resource Manager and/or the Project Manager.

  • Reviewed – Submitted Actuals have been reviewed. This Status is only available when a Timesheet has been reviewed by the Resource Manager.

  • Approved – Submitted/Reviewed Actuals were approved. This Status is only available when a Timesheet has been approved by the Project Manager.

  • Rework – Submitted Actuals were not accepted and sent back by the Resource Manager or the Project Manager to Team Members for rework.

Clicking on a Timesheet card in the Timesheet cards panel will display the Timesheet of the selected week in the Time Navigation panel.

Time Navigation panel

Depending on the Intervals and Zoom options selected by the Administrator in the System Settings, the Time Navigation panel can come with two view modes:

  • Week view mode

  • Month view mode

Time_Navigation_Panel.png

In Month view mode, in case of a week spanning over two months, you will be able to chose your preferred display by clicking on the More (MoreVertical) button.

Note

This setting is enabled by the Administrator in the System Settings workspace.

Each day comes with one of the following statuses:

  • Working – Actuals have been or need to be entered, moving the Timesheet from a non-working (inactive) phase to a working (active) phase.

  • Approved – Submitted/Reviewed Actuals were approved. This Status is only available when a Timesheet has been approved by the Project Manager.

  • Rework – Submitted Actuals were not accepted and sent back by the Resource Manager or the Project Manager to Team Members for rework.

  • Submitted – A Submit command has been executed, submitting the Actuals to the Resource Manager and/or the Project Manager.

  • Reviewed – Submitted Actuals have been reviewed. This Status is only available when a Timesheet has been reviewed by the Resource Manager.

Submit and Recall a Timesheet

Once all Actual Effort has been entered, you will be able to submit your timesheet by clicking on the Submit button.

Note

The availability of the Submit button when the Week or Month view modes are displayed depends on a setting set by the Administrator in the System Settings workspace.

Note

Depending on the options set by the Administrator in the System Settings workspace, a Recall command may be displayed, enabling Team Members to recall their Timesheet to apply some changes.

Warning

Submitting Timesheets blocks any changes that can be made to the Timesheet unless the Resource Manager or Project Manager asks for a revision, or the Team Member clicks on the Recall button.

Time Entry Rules

Administrators are able to assign Time Entry Rules to Resources. It will determine the rules that resources will have to follow when entering their actuals in their timesheets.

Rules will be enforced meaning that warning messages will be displayed when a rule is violated, and it will not be possible to submit the Timesheet unless the issues are corrected.

Note

Time Entry Rules are set in the Designer Time Tracking view.

Enforced Rules

Enforced_Rules.png

Submit a custom period

To submit a custom period:

  1. Hover the mouse over the day(s), then click on the last day you want to select to validate the selection.

  2. Click on the Submit Period button.

Submit_Custom_Period.png

To remove the selection, you can either click on the last day of the displayed period, or on the Clear selection (Clear_selection_button.png) button.

Warning

The Administrator can allow users to submit a custom period by switching on the "Allow Submit on Custom Period" setting available in the System Settings workspace, Project Settings folder, Time Tracking Options tab.

Note

The selection will always start from the first day of the displayed period.

Note

Once a custom period has been selected, the Week's Total Effort displayed at the activity level is read only. Therefore, users cannot enter their Total Actual Effort at the activity level if they have already partially submitted their timesheet.

Tasks panel

In the Tasks panel, you will be able to enter your Actual Effort, update your Remaining Effort, and import Activity logs.

Tasks_panel.png

By default, all tasks you have been assigned to for the selected time frame are displayed. They are grouped by Project.

Each task comes with one of the following statuses:

  1. Working – Actuals have been or need to be entered, moving the Timesheet from a non-working (inactive) phase to a working (active) phase.

  2. Approved – Submitted/Reviewed Actuals were approved. This Status is only available when a Timesheet has been approved by the Project Manager.

  3. Rework – Submitted Actuals were not accepted and sent back by the Resource Manager or the Project Manager to Team Members for rework.

  4. Submitted – A Submit command has been executed, submitting the Actuals to the Resource Manager and/or the Project Manager.

The following tools are also provided:

pin_active.png

Pin

Enables to pin tasks, so that they will always be displayed in the Tasks panel, even when you are not assigned to the task.

input_indicator_comment.png

Notes

Enables you to enter Notes.

The Notes icon is available when hovering on the top right hand side of the Actual Effort cell.

Add new tasks

The Tasks panel displays all tasks which you have been assigned on for the selected Time frame in the Time Navigation panel.

If you have worked on a task which was not planned, you can assign yourself to it.

Sciforma provides the ability to auto-assign resources on non-project related tasks so that users can submit complete Timesheets to include time off for vacation, sickness, etc.

To add some new tasks:

  1. Click on the +Task(s) button.

  2. In the Add to Timesheet popup, you will be prompted to chose the kind of task(s) you would like to add.

    1. Click on Projects to open the Projects list. By clicking on the desired project, the list switches to the corresponding project’s Tasks list. Click on a Task's name to add the task directly to the Timesheet, or select several tasks by ticking the corresponding checkboxes, and click on the Add task(s) to the Timesheet button.

      Note

      Assignments are only possible on Published Project Tasks.

    2. Click on the Non-project assignments button to open the Non-Project related tasks list (e.g. Vacation, Sickness, Jury Duty, etc.). Click on a Task's name to add the task directly to the Timesheet, or select several tasks by ticking the corresponding checkboxes, and click on the Add task(s) to the Timesheet button. The selected task(s) will be added to the Timesheet in a section named “Non-Project”.

      Note

      Tasks available in the Non-Project project are created by the Administrator.

The tasks closed by the Project Managers will behave as follows:

  • Closed tasks assignments with at least one non-zero Actual Hours value in the selected period will be displayed.

  • Closed tasks assignments with only zero Actual Hours values will be removed from the timesheet view regardless of whether there are planned hours or not.

  • Closed tasks will always be hidden when using the Add Assignment.

  • Closed tasks and tasks from closed projects will always be marked as “(Closed)” in the Tasks panel and will be read only.

Remove tasks

Team members have the opportunity to remove tasks from their timesheets even if Actual Effort has already been entered.

Note

When using the Remove tasks capability, note that tasks are not deleted from projects. They just aren't displayed in timesheets anymore.

Removing tasks is not allowed if the Timesheet status is Submitted, Reviewed, Approved or Applied.

  1. Select the task you want to remove by clicking on the task row.

  2. The row turns light blue.

  3. Click on the Remove button available at the bottom of the screen.

  4. A warning message is displayed allowing you to:

    1. Confirm the action by clicking on the Yes button.

    2. Cancel the action by clicking on the close22_md.png button.

Enter Actual Effort

  1. Click on the Actual Effort cell of the task for which you want to enter some Actual Effort.

  2. Enter a value.

Note

For tasks which you have been assigned to, a blue clock (input_indicator_planned-effort.png) will be displayed on the bottom right hand side of Actual Effort cells. Clicking on the blue clock will apply automatically the planned value.

You can also apply the planned effort to the whole period by clicking on the white clock (White_clock.png) displayed on the left hand side of the Remaining Effort cell of the task for which you want to enter the Planned Effort. Clicking on the white clock will apply automatically the planned value to all days.

Enter Actual Effort on Non-Working Days

  1. Click on the Actual Effort cell of the task for which you want to enter some Actual Effort.

  2. Enter a value.

Note

Once the user has entered some effort on a non-working day, the week's total effort and total number of days displayed in the "Submit" button will take into account the non-working day.

Warning

The Administrator can allow users to enter their actual effort on non-working days by switching on the "Allow Actuals on Non-Working Days" setting available in the System Settings workspace, Project Settings folder, Time Tracking Options tab.

Enter Actual Effort on the Week's Total

  1. Click on the Week's Total Effort cell of the task for which you want to enter the Week's Total Effort.

  2. Enter a value.

Note

The Total Effort will be split evenly on all working days even if the user has the possibility to enter some Actual Effort on non-working days, and the values previously entered on non-working days will be erased.

If the user then enters some actual effort in a non-working day Actual Effort cell, the total effort will be recalculated but will not be redistributed.

Enter Remaining Effort

If need be, you will be able to enter a Suggested remaining effort. Once submitted, this Suggested remaining effort may be applied to the Project by The Project Manager.

  1. Click on the Remaining Effort cell of the task for which you want to enter some Remaining Effort.

  2. In the Task popup, enter a new value in the Suggested remaining effort cell.

Activity Log

The Activity Log button allows you to display the hours you have dedicated to Agile Backlog Items and Work Items and otherwise facilitates how you update your timesheets.

Warning

Tasks and Team Members must be imported from Agile to another project using the Agile Synchronization feature in order for the corresponding data to be displayed in the Timesheet.

When the system uses the Agile or Work Items features, the Administrator can activate some options, which allows the Activity Log to be made available to end-users in the Timesheet workspace. Once the settings are activated, the Activity Log button is displayed.

In order to import Activity Logs:

  1. Click on the Activity Log button.

  2. In the Import activity logs popup, tick the checkboxes of the Agile Backlog Items or Work Items for which you you want to import the Activity logs.

    Note

    Clicking on the active Comments (notesUnread22_md.png) icon prompts a read-only pop-up that allows you to review the comment previously entered.

    Activity_Log_EN.png
  3. Click on the Import activity logs button. The corresponding Activity Logs will be automatically imported as Actual Effort into the Timesheet.

    Note

    Upon importing the Work Items Activity logs, the corresponding task will automatically be added to the spreadsheet.

    Note

    The Import Activity Logs button is only available if the Agile registered logs are different from the Timesheet Actual Effort.

    Note

    Activity logs will not appear in the Import Activity Logs popup for closed projects/tasks, except if:

    • Your Timesheet included a closed task to which you were already assigned.

    • The task’s Activity Log had been imported prior to the task being closed by the Project Manager.

    In this case, the activity’s effort will not be reimported.

If Activity Logs are related to tasks, you will be able to import them with the following button accessible when hovering over the Task's name.

Log_Task_EN.png

Rework Comments

Sometimes Actual Effort values submitted for a task are not accepted by the Resource Manager or the Project Manager and are returned for rework to the Team Member.

When sending back a Timesheet, the Resource Manager or the Project Manager will be able to write a comment to his/her Team Member.

These Rework Comments will be displayed to the Team Member in the Tasks panel when the Rework comment has been entered by the Project Manager and in the Time Navigation panel when the Rework comment has been entered by the Resource Manager.

Rework_Comment_2.png