How to enter Actual Effort non-uniformly

Under certain circumstances, a Project Manager might prefer to enter manually a Team member’s Actual Effort rather than using timesheets.

Warning

In order to enter Actual Efforts without using timesheets, it is compulsory to track first the Time as explained in the Time Tracking topic.

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select a project in the Project Data Selector.

  4. Select the task you want to track.

  5. In the Task panel, select the Assignments tab.

  6. In the Assignment card, click on the More (MoreVertical) button, and select the Edit command.

  7. In the Labor Assignment dialog box, enter some Actual Effort in each cell of the spreadsheet.

  8. Close the dialog box.

Warning

Depending on the Assignment Distribution type and the options set by the Administrator, the Remaining Effort or the Total Effort might be recalculated.