Resolve Resource Contention dialog box

The Resolve Resource Contention dialog box enables users to adjust resource utilization.

Here are the different options available in the dialog box.

Option

Description

Save Baseline 10 Before leveling

Select this option if you want to save the baseline of your original project schedule to a baseline before choosing the Resolve Resource Contention.

When you enable Baseline 10 this will update the Resource Leveling Report that is available in the Dashboards workspace.

Resources Leveled

You have the option to select all the resources in the system or select a filter that will be applied during Resolving Resource Contention.

Time Scale

You can choose the appropriate Time Scale (Hour, Day, Week, Month) for Resolving Resource Contention based on how detailed you assigned resources.

Used Scaled Availabilities

When selecting this option it allows you to specify a percentage of resources total availability when resolving resource contention within your project.

Honor Calendar Gaps

Sciforma will honor calendar gaps when enabled.