How to split a Task that is partially completed

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select a project in the Project Data Selector.

  4. Place the mouse pointer on the right-hand side of the task’s Start Date or on the right-hand side of the date on which its progress was entered in order to visualize the Update icon. GanttUpdateProgress.png

  5. Hold down the left mouse button and extend the completed portion of the task to the desired date.