Completed Date

The Completed Date is the date up to which actual effort, actual units, and actual costs may be entered for the task.

Note

The Completed Date is not necessarily the same date as the As of Date.

When entering a Completed Date, Sciforma will update the Actual Start if an Actual Start has not already been entered, and the Completed Duration and Remaining Duration fields will also be updated.

If a Completed Date is entered identical to the Scheduled Finish of a task, the Actual Finish is updated.