OTD Baseline

The OTD Baseline is the Baseline used to calculate the OTD Status.

The OTD Baseline can be set at the project level in the Administration workspace, Setup tab, Phases & Gates Advanced Attributes popup. In there, the user can either:

  • Choose to use the Current Baseline (if editable). Note: This field is editable only if the Enable Project OTD Baseline Selection setting has been activated by the Administrator in the System Settings workspace, Project Settings folder, Display Preferences tab.

  • Select an OTD Baseline (only available when the Current Baseline switch button is deactivated).

In addition to providing the OTD Status, selecting an OTD Baseline will automatically fill in the OTD Baseline Start and OTD Baseline Finish fields of the Work workspace, Phases & Gates tab, Phases/Gates mode.