How to modify the Gate Workflow State

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Phases & Gates tab.

  3. Select a project in the Project Data Selector.

  4. Select the Phases/Gates mode (viewmode_activeroadmap22_md.png).

  5. Click on the Enable Filters (FilterGrey) button, if you need to activate filters.

  6. Click in the cell of the Workflow State field of the Gate for which you want to modify the workflow.

  7. Click on the (ArrowDownSmall) arrow to display the available Workflow State.

  8. Select a new Workflow State.

Note

Upon approving a Gate, the user will be prompted to enter the date to consider as the Gate Actual date (Planned date, today’s date, or a specific date) and the % Completed will be fulfilled with a 100% completion.

Note

Upon changing the workflow state to Approved, the Manage Baselines dialog box is displayed. It enables users to save a new baseline.

Note

The user will not be able to approve a Gate if all the Deliverables marked as “Mandatory” are not 100% Completed.