How to split a Task that is partially completed

  1. Log in to the HTML5 client.

  2. Select the Projects Center workspace and open the Project Card.

  3. Select the Gantt tab.

  4. On the Gantt bar, place the mouse pointer on the right-hand side of the task’s Start Date or on the right-hand side of the date on which its progress was entered and hold down the Shift key to visualize the Split (Split_a_task.png) icon.

  5. Hold down the left mouse button and extend the completed portion of the task to the desired date.