How to replace Cost Items Assignments

  1. Log in to the HTML5 client.

  2. Select the Projects Center workspace and open the Project Card.

  3. Select the Gantt tab.

  4. Select a task in the Gantt spreadsheet to display the Task panel.

  5. Select the Transactions & Cost Items tab (Cost).

  6. In the Cost Item Assignment card, click on the More (MoreVertical) button, and select the Replace command to open the Replace Cost Items dialog box.

  7. Replace the Cost Item assignment with one or several Cost Items.

  8. Close the dialog box.