Sometimes Actual Effort values submitted for a task are not accepted by the Project Manager and are returned for rework to the Team Member. Rework is only available if the Status of the Timesheet is Submitted, Reviewed, or Approved.
Log in to the HTML5 client.
Select the Projects Center workspace and open the Project Card.
Select the Task tab, Tracking sub-tab.
Select a project in the Project Data Selector.
By default, the Timesheets Overview displays the Resource Timesheets for the Current Week. Select another time frame if needed.
The Timesheets Overview provides the list of Resource Timesheets, grouped by overall Status enabling bulk actions
Click on the Rework button to send the timesheets back to the Team Members.
The Status of the Timesheet changed to Rework.
The Timesheets are moved to the Rework Status section.
In the Timesheets Overview, click on the Resource's name to switch to the Timesheet Details full screen view.
Click on the Rework button to send the timesheet back to the Team Member.
The Status of the Timesheet changed to Rework.
NoteNote that Non-Project tasks already approved by the Resource Manager cannot be sent to Rework.
TipThe Project Manager can also Approve or Approve & Apply a specific Task Timesheets by clicking on the corresponding More () button.
The Timesheet is moved to the Rework Status section.