How to mark a Mitigation Item as completed

  1. Log in to the HTML5 client.

  2. Select the Projects Center workspace and open the Project Card.

  3. In the Risks tab, click on the Risk Name of the Risk card to open the Risk dialog box.

    Risk_card___Open.png
  4. In the Mitigation section, click on the MITIGATION PLAN button to open the Mitigation Plan popup.

  5. Select the Mitigation Items sub-tab.

  6. Click on the Check mark button to turn it green (CheckFullGreen) and mark it as Completed.

  7. The Completed Date is filled automatically.