How to convert a Contingency Item into a Contingency Action

  1. Log in to the HTML5 client.

  2. Select the Projects Center workspace and open the Project Card.

  3. In the Risks tab, click on the Risk Name of the Risk card to open the Risk dialog box.

    Risk_card___Open.png
  4. In the Contingency section, click on the CONTINGENCY PLAN button to open the Contingency Plan popup.

  5. Select the Contingency Items sub-tab.

  6. Click on the More (MoreVertical) button available on the Contingency Item row and select Convert.

  7. The Action Name is fulfilled automatically in the Action popup.

  8. Enter the necessary information.

  9. Click on the DONE button to close the Action popup.

Note

The Contingency Item is not displayed anymore in the Contingency Plan popup as it has been converted into a Contingency Action.