How to split a Task that is partially completed

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select a project in the Project Data Selector.

  4. Place the mouse pointer on the right-hand side of the task’s Start Date or on the right-hand side of the date on which its progress was entered and hold down the Shift key to visualize the Split (Split_a_task.png) icon.

  5. Hold down the left mouse button and extend the completed portion of the task to the desired date.