How to enter the Actual Finish of a Task

Warning

Once an Actual Finish is entered, the Completed Date is automatically updated to the same date, and the % Completed is automatically updated to 100%. This reflects the completion of the task.

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select a project in the Project Data Selector.

In the Task panel

  1. Select the task you want to track.

  2. In the Task panel, select the Task Form tab (TaskFormTabActive).

  3. In the Tracking section, select a date in the Actual Finish field.

In the Task Details dialog box

  1. Click on the Cmd (GearGantt) gear button of the task you want to track.

  2. Select the Edit Task details command to open the Task Details dialog box.

  3. In the Definition folder, Tracking section, select a date in the Actual Finish field.