Log in to the HTML5 client.
Select the Finance workspace.
Select a Project in the Project Data Selector.
Click on the DETAILS button available in the Costs tile to open the Dashboards view.
Select the Costs tab which provides a different display depending on whether or not the Cost Centers () display option is activated.
Cost Centers Off – The spreadsheet will provide a view whereby the user can easily compare the Budget with the Project Cost and the Forecast Cost.
NoteProject Cost = Resource Assignments Cost + Cost Item Assignments Cost + Cost Transactions
For further information, please refer to the Resources Scheduling, Cost Items, and Cost Transactions topics.
Project Forecast Cost = Labor Forecast + Cost Item Forecast + Transaction Forecast
For further information, please refer to the Forecast topic.
Cost Centers On – The spreadsheet will be broken down by Cost Centers.
Select the Budget tab to review at a glance the potential shifts between the project's Budget and Cost values.