Log in to the HTML5 client.
Select the Projects Center workspace and open the Project Card.
Select the Phases & Gates tab.
Select the Deliverables mode ().
NoteAll Deliverables created for the selected project will be displayed.
Click on the New () button to create a new deliverable, if need be.
In the Work Item dialog box, enter the needed information.
Click on the Edit () button of the Deliverable you want to attach to a Gate.
In the Work Item dialog box, Phases & Gates section, click on the () button to display the list of Gates.
Select a Gate.
Switch on the Mandatory option if need be.
WarningBy doing so, the user will not be able to approve a Gate if all the Deliverables marked as “Mandatory” are not 100% Completed.
Close the dialog box.
Click on the Edit () button of the Deliverable you want to mark as completed.
In the Work Item dialog box, click on the Workflow button and select the Complete the Deliverable command.
Close the dialog box.