How to create the Task to Task Dependency – Image Mapping

  1. Log in to the HTML5 client.

  2. Select the Projects Center workspace and open the Project Card.

    The Project Card must be the Project Card of the project which is the Target of the dependency.

  3. Select the Gantt tab.

  4. Create a new task, so that the data coming from the Source object will be displayed on this task.

    How_to___Image_Mapping_1.png
  5. In the Gantt spreadsheet, click on the Cmd (GearGantt) button, and select the Create Dependency command.

  6. In the Create a New Dependency popup, select:

    1. Mapping Type: Image

    2. Task to Task dependency

    Note

    If a Default Mapping has been selected in the Setup sub-tab you can leave the Mapping Type field blank.

  7. Select the Project Source in the list, and then the Task Source.

  8. The Gear (GearGanttDependency) icon indicates that the task has a dependency with another object. This specific Gear icon is only displayed on the Target task.

    The two symbols (triangles) on the Gantt chart show the start date and end date of the project as scheduled by the Program Manager.

    Note

    A contract could also be created between the two objects, giving therefore more formal targets (Dates, Budget, and Deliverables).

  9. Project Managers will then have to schedule their projects taking into account the data coming from the Program. Projects will then have to be published.