How to add Critical Chain Resource Links

Note

This action adds explicit links to the Critical Chain at the points where a resource dependency exists. This command should be used after having identified the Critical Chain and before inserting buffers.

  1. Log in to the HTML5 client.

  2. Select the Projects Center workspace and open the Project Card.

  3. Select the Gantt tab.

  4. Click on the Critical Chain (ConnectionsGrey) button, and select the Add Critical Chain Resource Links command.