How to create an Activity Log

  1. Log in to the HTML5 client.

  2. Select the Projects Center workspace and open the Project Card.

  3. Select the Work Items tab.

  4. Click on the number of open Change Requests in the upper right corner of the Change Requests Chart section to open the Work Item full screen view, Inbox tab.

  5. Select a Change Request in the Work Items List panel.

  6. In the Work Item Details view, click on the Activity Log button to activate the Activity Log section.

  7. In the Activity Log section, click on the New (NewProject) command in order to break down the Change Request work.

  8. Select a User to assign the work to another Resource if need be. Enter some Actual Effort if you want to import this Effort directly in the Timesheet.

    Note

    Selecting a User in an Activity Log of a Work Item will not display the item in his/her Work Items Home Page.

  9. Click on the (search_clear22_md.png) button to close the full screen view.