How to chose the Risks to mitigate

Analyze the Probability/Severity Matrix

  1. Log in to the HTML5 client.

  2. Select the Projects Center workspace and open the Project Card.

  3. Select the Risks tab.

  4. Click on the DASHBOARDS button, available in the Project Information panel.

  5. In the Dashboards full screen view, select the Matrix tab.

  6. Click on a number displayed in the Matrix cell to open the Risks full screen view, where only Risks with the selected combination of Severity and Probability are shown.

Compare the Current Risk Level with the Mitigated Risk Level

  1. Log in to the HTML5 client.

  2. Select the Projects Center workspace and open the Project Card.

  3. Select the Risks tab.

  4. In the Risks tab, click on the Risk Name to open the Risk card.

    Risk_card___Open.png
  5. Compare the Current Risk Level with the Mitigated Risk Level.

Prioritize the Risks regarding their Attributes

  1. Log in to the HTML5 client.

  2. Select the Projects Center workspace and open the Project Card.

  3. Select the Risks tab.

  4. Click on the RISKS > button, available in the Project Information panel to open the Risks full screen view.

  5. Select the Grid tab.

  6. Select an option in the Display options list in order to display different Risk attributes.

    Priorization___Risks_full_screen_view.png