How to analyze Resources Utilization with the Resource Panel

  1. Log in to the HTML5 client.

  2. Select the Projects Center workspace and open the Project Card.

  3. Select the Gantt tab.

  4. Click on the Manage_people.png button available in the Gantt toolbar to display the Resource Panel.

  5. Choose the data you wish to display by selecting a field, a unit, and a scope.

    The available field, unit, and scope are the following:

    • Field:

      • Total Effort

      • Remaining Effort

      • Available Effort

    • Unit:

      • Hours

      • Days

      • Percentage

    • Scope:

      • Selected Project

      • Selected and Published Projects

  6. Analyze the resource utilization.

    Settings

    Data cells for the Total Effort and Available Effort will be colored according to the colored indicators set by the Administration in the System Settings workspace, General Settings folder, Colored indicators tab, Gantt Resource Utilization Preferences section.

    Note

    Users will be able to open the Legend details by clicking on the Legend button available on the bottom right-hand side of the distributed grid.

Note

The Resource Panel distributed grid is read-only.