How to relate a Deliverable to a Task

Settings

The steps described below are the ones when the Enable Work Items Home Page Charts option is enabled by the Administrator in the System Settings workspace, Work Management Settings folder, Global Options tab.

  1. Log in to the HTML5 client.

  2. Select the Projects Center workspace and open the Project Card.

  3. Select the Work Items tab.

  4. Click on the number of open Deliverables in the upper right corner of the Deliverables Chart section to open the Work Item full screen view, Inbox tab.

  5. Select a Deliverable in the Work Items List panel.

  6. In the Deliverable Card, select a task in the Related Task field if you want to relate the Deliverable to a task. In doing so, the Deliverable will be available in the Gantt side panel.

    Note

    This field is only available if you create a Deliverable related to a Project.