Log in to the HTML5 client.
Select the Work workspace, Gantt tab.
Select the project which is the Target of the dependency in the Project Data Selector.
In the Gantt spreadsheet, click on the Cmd () button of the task for which you want to create a dependency, and select the Create Dependency command.
NoteCreating an Image mapping dependency will display symbols above the task.
The Project Manager will then have to adjust the start and finish date of the task.
In the Create a New Dependency popup, select:
Mapping Type: Image
Project to Task dependency
NoteIf a Default Mapping has been selected in the Project Administration dialog box, you can leave the Mapping Type field blank.
Select the Project Source in the list.
The Gear () icon indicates that the task has a dependency with another object. This specific Gear icon is only displayed on the Target task.