Warning
Only Cost Items that are part of the Project Team can be assigned to tasks.
Log in to the HTML5 client.
Select the Work workspace, Gantt tab.
Select a project in the Project Data Selector.
Select a task in the Gantt spreadsheet to display the Task panel.
Select the Transactions & Cost Items tab (
).
Click on the NEW button to open the Assign Cost Items dialog box.
Select a Cost Item in the Cost Items list by clicking on it.
In the Cost Item card, modify the Rate (
) and the Total Units (
) if needed.
Click on the DONE button to close the dialog box.
The Cost Item has been added to the Task panel.