Note
To proceed to the following actions, you need to have created the tasks first.
Log in to the HTML5 client.
Select the Work workspace, Phases & Gates tab.
Select a project in the Project Data Selector.
Select the Phases/Gates mode (
).
Click on the Enable Filters (
) button.
In the Filters popup, switch on the Show All Tasks option, and close the popup.
Click on the More (
) button of the task you want to turn into a Gate, and select the Turn Task into Gate command.
Warning
In order for the OTD values to be available, you need to save a Baseline ().