Remaining Duration

Tasks are monitored on their remaining duration, not their percentage complete. Resources report upon tasks in progress based on the number of days they estimate it will take to complete the task. If the Remaining Duration stays static or increases, then Project Managers and Resource Managers “watching the buffers” know exactly where a blockage or potential delay is occurring and can take decisive action quickly to recover.