How to level resources automatically

Tip

Do not forget to lock your project before leveling in the event you want to undo the result if unsatisfactory.

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select a project in the Project Data Selector.

  4. In the Gantt toolbar, click on the More (MoreHorizontal) button, and select the Level Resources command to open the Level Resources dialog box.

  5. Select the needed options.

  6. Click on the OK button to proceed to the resources leveling.

Tip

If you want to compare the Gantt chart before and after the resources leveling, select the Save baseline 10 before leveling option.