How to enter Remaining Effort uniformly

Under certain circumstances, a Project Manager might prefer to enter manually a Team member’s Remaining Effort rather than using timesheets.

Warning

In order to enter Remaining Efforts without using timesheets, it is compulsory to track first the Time as explained in the Time Tracking topic.

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select a project in the Project Data Selector.

  4. Click on the Cmd (GearGantt) gear button of the task you want to track and select the Edit Task details command.

  5. In the Task Details dialog box, select the Labor Assignments folder.

  6. Enter the Remaining Effort in the Remaining Effort field.

Warning

Depending on the Distribution Type and the options set by the Administrator, the Total Effort or the task's Duration might be recalculated.