[en] Log in to the HTML5 client.
[en] Select the Work workspace, Register Balkenplan.
[en] Select a project in the Projektdatenselektor.
[en] In the Hauptsymbolleiste, click on the Manage Baselines () button to open the Dialogfenster Basis verwalten.
[en] In the Baseline card of the baseline you want to shift, click on the More () button, and select the Shift command.
[en] In the Shift Baseline popup, select the date you wish to shift the Baseline to.
Anmerkung[en] The Shift to section offers two ways to shift the Baseline:
[en]Specific date
[en] Allows the user to shift the Baseline to a specific date.
[en]Current project's start date
[en] Allows the user to shift the Baseline to the project's start date.
[en] Click on the SHIFT button.