How to align a Project to an Objective

When a project is attached to an Objective, its level of contribution to this objective can be set thanks to its Project Alignment Level.

It will help evaluate and understand levels of contribution, and decide whether or not the project is worth being funded.

As a Strategy Manager

  1. Log in to the HTML5 client.

  2. Select the Objectives workspace, Projects sub-tab.

  3. Select an Objective in the selector.

  4. Click on the EDIT button of the Alignment tile available in each Project card.

  5. Modify the Alignment Level in the pick-list of the Edit Alignment Values popup.

  6. The Strategic score is computed and represents the combination of the Alignment level and the Corporate Objective's Final Weight.

  7. Click on the CLOSE button.

As a Project Manager

  1. Log in to the HTML5 client.

  2. Select the Home Page workspace, Objectives tab.

  3. Select a project in the selector.

  4. Click on the EDIT button of the Alignment tile available in each Objective card.

  5. Modify the Alignment Level in the pick-list of the Edit Alignment Values popup.

  6. The Strategic score is computed and represents the combination of the Alignment level and the Corporate Objective's Final Weight.

  7. Click on the CLOSE button.