Warning
Once an Actual Finish is entered, the Completed Date is automatically updated to the same date, and the % Completed is automatically updated to 100%. This reflects the completion of the task.
Log in to the HTML5 client.
Select the Work workspace, Gantt tab.
Select a project in the Project Data Selector.
Select the task you want to track.
In the Task panel, select the Task Form tab (
).
In the Tracking section, select a date in the Actual Finish field.
Click on the Cmd (
) gear button of the task you want to track.
Select the Edit Task details command to open the Task Details dialog box.
In the Definition folder, Tracking section, select a date in the Actual Finish field.