Update Progress

The Update Progress command displays the Update Progress dialog box where the user can update the completion date of tasks or delay remaining portions of tasks to start on a specified date.

UpdateProgress.png

Scope

Allows the user to update all the project’s Tasks, or only the Tasks he/she has previously selected in the Gantt spreadsheet.

Update method

Allows the user to define how he/she wishes to update the progress:

  • Complete up through progress date – Updates the completion up to the entered Progress date included.

  • Delay remaining to start on progress date – Delays the remaining portions of the tasks after the entered Progress date (next day).

Set project "As Of Date" to the progress date

Upon selecting this option, the project’s As of Date will be updated to correspond to the specified Progress date.