Calendar

Calendars specify the days and hours during which work will take place on the project, task, assignment, etc.

For example, if the project calendar defines January 1st as a holiday, no work will take place on that date.

However, calendars can also be assigned to other Sciforma data objects, such as tasks, resources, cost items, and assignments, in which case the project calendar could be overridden as follows:

  • If any of the project's tasks has a calendar specified (but there are no assignments), that calendar determines the days and hours during which work will take place on that task.

  • If any of the tasks has a labor or cost item assignment, the corresponding resource or cost item calendar determines when the assigned labor/cost items will work or be used on that task.

  • If any of the assignments specify an assignment calendar, the labor assignment or cost item assignment calendar determines the days and hours during which those assigned labor/cost items will work or be used on that task.

Note

Calendars are created by the Administrator in the Designer Calendars view.