Required Date

The Required Date field allows project managers to enter the target completion date for a task. If the Scheduled Finish date for a task or a key milestone extends beyond the Required Date, Sciforma will display a negative float value.

In the Gantt chart's graphic pane, the Required Date is represented by the following yellow triangle:

Required_Date.png