Default Resource Assignment Cost Source

The Default Resource Assignment Cost Source allows the user to define the default source for the Resource Assignment Actual Cost.

The following sources can be used to calculate the Resource Assignment Cost:

Resource

Takes into account the Resource Cost, as defined in the Resource Identification dialog box to calculate the Resource Assignment Cost.

Labor Assignment

Takes into account the Resource Cost Source at the Assignment level.

Job Classification

Takes into account the Job Classification defined in the Labor Assignment dialog box.

Organization

Takes into account the Organization defined in the Labor Assignment dialog box.

Effective Job Classification

Takes into account the Effective Job Classification (i.e., the Resource’s Job Classification) of the assigned Resource.

Effective Organization

Takes into account the Effective Organization (i.e., the Organization to which the Resource belongs) of the assigned Resource.