How to delete Task relationships

Important

If your Schedule Mode is "Critical Chain", do not forget to select the Planning Mode. The Switch to Tracking Mode (alarm22_md.png) button must be displayed in the Main toolbar.

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select a project in the Project Data Selector.

  4. Select the Scheduler (viewmode_activegantt22_md.png) mode.

In the Gantt chart

  1. Click on the link to display the Task Link dialog box.

  2. Click on the DELETE button.

In the Task Details dialog box

  1. In the Gantt Spreadsheet, click on the Gear (GearGantt) icon of the task for which you want to delete the link, and select the Edit Task Details command.

  2. In the Task Details dialog box, select the Definition folder, Predecessors and Successors sections.

  3. Select the predecessors or successors by ticking their checkboxes.

  4. Click on the Delete (DeleteRed) button.

  5. Close the Task Details dialog box.

Using the Links command

  1. Select two tasks in the Gantt spreadsheet and click on the Links (LinkGrey) button available in the Gantt toolbar.

  2. Select the Chain Delink command to remove the links between the selected tasks.