Release Dates

Release dates fields are the following:

  • Current Finish – The Current Finish is the latest Finish Date of the Iterations belonging to the Release.

  • Current Start – The Current Start is the earliest start date of the iterations belonging to the release.

  • Target Finish – The Target Finish is the date the release is supposed to be delivered.

  • Target Start – The Target Start is the date the release is supposed to start.

Note

When synchronizing the Agile objects in the Gantt view, the Agile tab of the side panel will display the Release Target Finish if any, otherwise it will display the Actual Finish.