Log in to the HTML5 client.
Select the Projects Center workspace and open the Project Card.
In the Project Card Main toolbar, click on the Manage Baselines () button to open the Manage Baselines dialog box.
Enter a Baseline Name and click on the SAVE BASELINE button.
The baseline is added to the list in the form of a card.
Close the dialog box.
In the Gantt chart, the current baseline is displayed as a purple line.
When the user selects a Task in the Gantt chart before accessing the Manage Baselines dialog box, the Scope option will become available, allowing the user to choose whether he/she wants to save the Baseline values for the whole project, or only the previously selected tasks.
When there are no more empty Baseline slots (the 14 baselines have been saved), the Save section disappears. The user can click on the Capture () button of a Baseline card to overwrite an existing Baseline.