The Backlog Items % Completed (at the Project or Iteration level) is computed as follows: Number of Completed Backlog Items / Total Number of Backlog Items x 100
Story Points
The Backlog Items % Completed (at the Project or Iteration level) is computed as follows: Number of Completed Story Points / Total Number of Story Points x 100