Total Cost

At the assignment level, this field indicates the total costs attributable to this assignment through both the completed portion and remaining portion.

At the task level, this field indicates total costs attributable to this task through both the completed portions and remaining portions of all assignments (Cost Item, Labor assignments, and Transactions costs). In other words, this is the sum of the task's cost item assignments’ Total Cost values plus the sum of the task's labor assignments’ Total Cost values, plus the sum of all the task's transactions’ Total Cost values.

At the project level, this field displays the total costs attributable to this project through both the completed portions and remaining portions of all assignments (Cost Item assignments, Labor assignments, and Transactions costs). In other words, this is the sum of the project's cost item assignments’ Total Cost values plus the sum of all the project's labor assignments’ Total Cost values plus the sum of all the project's transactions’ Total Cost values.