How to synchronize the Master Planning

Whether the project managers updated the projects or the Executives edited and published the projects from the Project Full Screen view, the user needs to synchronize the information for the modifications to be taken into account in the Master Planning.

If at least one Task of the Master Planning is not synchronized with the corresponding Source object, the Sync All button is displayed at the bottom of the side panel, allowing the user to synchronize the dependency.

  1. Log in to the HTML5 client.

  2. Select the Master Planning workspace.

  3. Select a Master Planning in the Project Data Selector.

  4. DO NOT select any task in the Gantt spreadsheet.

  5. Click on the Sync_All_button.png button available in the Side panel.