How to enter Tasks Date Constraints

Important

If your Schedule Mode is "Critical Chain", do not forget to select the Planning Mode. The Switch to Tracking Mode (alarm22_md.png) button must be displayed in the Main toolbar.

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select a project in the Project Data Selector.

  4. Select the Scheduler (viewmode_activegantt22_md.png) mode.

In the Task panel

  1. Select the task for which you want to enter a date constraint.

  2. In the Task panel, select the Task Form tab (TaskFormTabActive).

  3. In the Task section, enter a date in the following fields if needed: Start No Earlier Than, Must Start On, Required Date.

In the Task Details dialog box

  1. In the Gantt Spreadsheet, click on the Gear (GearGantt) icon of the task for which you want to enter a date constraint, and select the Edit Task Details command.

  2. In the Task Details dialog box, select the Definition folder.

  3. Enter a date in the following fields if needed: Start No Earlier Than, Must Start On, Required Date.

  4. Close the Task Details dialog box.