How to modify the Assignment Total Effort

Important

If your Schedule Mode is "Critical Chain", do not forget to select the Planning Mode. The Switch to Tracking Mode (alarm22_md.png) button must be displayed in the Main toolbar.

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select a project in the Project Data Selector.

  4. Select a task in the Gantt spreadsheet to display the Task panel.

  5. Select the Assignments tab (viewmode_activeresourceutilization22_md.png).

  6. In the Assignment card, modify directly the Assignment Total Effort (ganttSidePanel_icons_tabs_panels_daterange22_md.png).

  7. OR, click on the More (MoreVertical) button, and select the Edit command to open the Labor Assignment dialog box where the Total Effort can also be modified.