How to define Labor Forecast

  1. Log in to the HTML5 client.

  2. Select the Finance workspace.

  3. Select a Project in the Project Data Selector.

  4. Click on the EDIT button of the Forecast tile to open the Forecast dialog box.

  5. Select the Labor sub-tab.

If the view is empty

  1. Select one of the following pivot:

    1. None – The table will propose only one line to enter a global Forecast Cost.

    2. Organization – The table will allow to define the Forecast Cost by Organization.

    3. Job Classification – The table will allow to define the Forecast Cost by Job Classification.

    4. Cost Center – The table will allow to define Forecast Cost by Cost Center.

  2. In the Create a New Labor Forecast popup, select of the following options:

    1. New – A new row will be added to the spreadsheet.

    2. From Template – Choose a template in the Global Forecast Template selector.

      Note

      This option is only available if Forecast Templates have been defined by the Administrator.

    3. From Total Labor Cost – Total Labor Cost will be imported automatically as Forecast values.

  3. Enter Forecast Values in the spreadsheet distributed cells.

If the view is already fulfilled

Note

A pivot (Organization, Job Classification, or Cost Center) has already been defined. If you change the pivot, all the existing Forecast for this Category will be deleted.

  1. Click on the New (NewProject) button to add a row to the spreadsheet.

  2. Enter Forecast Values in the spreadsheet distributed cells.