Time Navigation Toolbar

The Time Navigation toolbar allows users to manage their time frames (as with Timesheets, for instance) in time-distributed views. The designs and options these toolbars offer might vary from one view to another.

Here is a list of capabilities that the toolbars offer:

Today

Today

Button that returns the user to the current time period

JumpTo

Jump to Date

Popup wherein the user can select a specific date to “jump to”. Once the selection is validated, the view switches to the corresponding time period.

Custom

Once activated, gives the user the ability to enter custom dates.

Note

Depending on the toolbar, the custom option can allow the user to either enter a custom Start Date (the interval will be the one set manually) or to enter both a Start and a Finish date (the interval to be automatically calculated by Sciforma).

IntervalColor

Intervals

Picklist that allows the user to select the interval (i.e., Day, Week, Month, Quarter, or Year).

IntervalNumber

Number of Intervals

Picklist, wherein the user can select the number of intervals to display. This number can range from 1 to 12.

It is also possible to go from one time period to another by using the navigation Previous (PreviousChevron) and Next (NextChevron) arrows.

Time_Navigation_arrows.png

In some views, the Presets (Presets) button of the time navigation toolbar is provided, allowing the user to directly set the displayed timeframe as follows:

Selected Preset Value

Time frame Displayed

Current Year

Displays the current year in months, from January to December.

(Intervals: Month; Number of Intervals: 12)

Current Quarter

Displays the current quarter in months.

(Intervals: Week; Number of Intervals: 12)

Current Week

Displays all the current week in days.

(Intervals: Day; Number of Intervals: 7)

6 Months from Project Start

Displays the next six months after the selected project’s Start date.

(Intervals: Month; Number of Intervals: 6)

6 Quarters from Project Start

Displays the next six quarters after the selected project’s Start date.

(Intervals: Quarter; Number of Intervals: 6)

6 Years from Project Start

Displays the next six years after the selected project’s Start date.

(Intervals: Year; Number of Intervals: 6)

6 Months from now

Displays the next six months from the beginning of the current month.

(Intervals: Month; Number of Intervals: 6)

6 Quarters from now

Displays the next six quarters from the beginning of the current quarter.

(Intervals: Quarter; Number of Intervals: 6)

6 Years from now

Displays the next six years from the beginning of the current year.

(Intervals: Year; Number of Intervals: 6)

Entire Project

Displays the time frame from the project's Start to the Project's Finish date.