How to modify Tasks Schedule types

By default, when a task is created, it will have the ASAP (As Soon As Possible) Schedule type. However, there are other options available regarding Schedule Type.

Important

If your Schedule Mode is "Critical Chain", do not forget to select the Planning Mode. The Switch to Tracking Mode (alarm22_md.png) button must be displayed in the Main toolbar.

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select a project in the Project Data Selector.

  4. Select the Scheduler (viewmode_activegantt22_md.png) mode.

  5. In the Gantt Spreadsheet, click on the Gear (GearGantt) icon of the task for which you want to modify the Schedule Type, and select the Edit Task Details command.

  6. In the Task Details dialog box, select the Definition folder.

  7. Select a Schedule Type in the Schedule Type field picklist.